Laserfiche WebLink
19 <br /> Contract Time <br /> Original contract time of this project was for 210 calendar days. Seventy Three,(73), <br /> additional calendar days are being added to the contract time due to the fact that the <br /> original contract drawings were not of sufficient information and detail to provide <br /> structural steel shop drawings in a timely fashion. The net result was late delivery of <br /> structural steel to the jobsite. <br /> The above additional cost of$120,232.64 constitutes all additional cost of any kind <br /> resulting from adding 73 calendars days to the contract time, from the above <br /> described work changes directives. <br /> 12 6 <br /> Exhibit A <br />