Washington Slate Department of Transportation Page 1 Six Year Transportation Improvement Program
<br /> Agency Everett From 2002 to 2007
<br /> County No. 31 Hearing Date
<br /> City No. 420 Adoption Date
<br /> MPO PSRC Resolution No.
<br /> Project Identification Project Costs in Thousands of Dollars Federally Funded
<br /> A. Federal Aid No. Fund Source Information Expenditure Schedule Projects Only
<br /> B. Bridge No. Federal Funding Local Agency
<br /> C. Project Title RAN
<br /> D. Street/County Road Name or Number Improve- Phase Federal Federal State 4th Required
<br /> Functional Priority E. Beginning MP or road-Ending MP or road men/ Total Utility Project Start Fund Cost by Fund State Local Total 1st 2nd 3rd thru Envir. Date
<br /> Class Number F. Describe Work to be Done Type Status Length Codes Phase (mm/dd/yyy Code Phase Code Funds Funds Funds (2002) (2003) (2004) 6th Type (MM/YY)
<br /> 1 1 2 3 4 5 a 7 a 9 10 11 12 13 14 15 16 17 18 19 20 21
<br /> 11 1 STPUL-1998(017) 2 phases in project 31 S 8 PE 5/1/99 DEMO 1,000 250 1250 250 CE No
<br /> various PE 5/1/99 STP(U) 247 38 285
<br /> Interstate 5 Corridor Improvement Study
<br /> 1-5
<br /> 112th St.SE to 12th St.NE
<br /> Design Report and Environmental Review al l-5 corridor Totals 1,247 288 1,535 250
<br /> 11 2 3 phases in project 4 S 5.6 0 PE 1/1/99 5,000 5,000 3,500 1,500
<br /> various RW 11/1/01 7,000 7,000 3,500 3,500 Yes
<br /> 1-5 Median HOV Lanes and Auxiliary Lanes CN 8/1/03 7,000 23,000 28,000
<br /> 1-5 58,000 58,000
<br /> SR 526 to US 2
<br /> Design and construct Medan HOV lanes end GP aux. Totals _ 75,000 70,000 7,000 12,000 23,000 28,000
<br /> 11 3 3 phases in project 3 P 0.1 0 PE 1/1/02 4,000 4,000 2,000 2,000
<br /> 5/630 P RW 1/1/03 4,000 4,000 2,000 2,000 No
<br /> I-5/41st Street SE Interchange T CN Jan-04 27,000 5,000 32,000 10,000 25,000
<br /> . 1-5,41st Street
<br /> 1-5 at 41st Street to 1-5 at 41st Street _
<br /> Design and construct Interchange Improvements Totals _ 35,000 5,000 40,000 2,000 3,000 10,000 25,000
<br /> 11 4 3 phases in project 3 P 0.1 0 PE 9/1/01 2,000 2,000 2,000
<br /> RW 8/1/02 2,000 2,000 2,000 Yes
<br /> 1-5/100th Street SE HOV Access/undercrossing CN 2/1/03 16,000 5,000 21,000 2,000 19,000
<br /> 1-5,100th Street SE
<br /> 1-5/100th Street SE to 1-5/100th Street SE
<br /> Design and construct HOV access/undercrossing Totals 20,000 5,000 25,000 4,000 2,000 19,000
<br /> 11 5 3 phases in project 3 P 0.1 0 PE 1/1/99 2,547 252
<br /> 5/620 (Sound Transit is lead on project) P RW 1/1/00 427 205 Yes
<br /> 1-5/112th St.Direct Access HOV-P&R/Flyer Stop T CN 1/1/03 9,969 8,451 750
<br /> 1-5,112th Street SE 25,705 25,705
<br /> I-5/112th Street SE to I-5/112th Street SE
<br /> Design/ConstructHOV Ramps,P&R Lot,Flyer Stop Totals 25,705 25,705' 2,974 10,426 8,451 750
<br /> 11 6 3 phases in project 3 P 0.3 0 PE 1/1/04 4,000 4,000 2,000 2,000
<br /> 5/640 RW 6/1/04 5,000 5,000 2,5001 2,500 Yes
<br /> 1-5/US 2 Interchange CN 6/1/05 26,000 26,000 1 26,000
<br /> 1-5,US 2,Hewitt Avenue,Everett Avenue
<br /> •
<br /> 1-5 at US 2 Interchange to I-5 at US 2 Interchange i _
<br /> Improve On-ramps,Local Arterials,a Interchange _ !. Totals 35,000 35,000 4,500; 30,500
<br /> •
<br /> 11 7 3 phases in project 3,6 P 0.3 0 PE' 1/1/05 4,000 4,000 ' 4,000
<br /> RW 6/1/05 6,000 6,000 6,000 No
<br /> 1-5/Downtown Everett off-ramp reconfiguration CN 6/1/07 20,000 5,000 25,000 25,000
<br /> 1-5 at Pacific,Hewitt,Everett Avenues
<br /> Pacific Avenue to Everett Avenue
<br /> Major reconfiguration of I-S offramps for Downtown Totals 30,000 5,000 35,000 35,000