Laserfiche WebLink
PORT OF EVERETT <br />W MARINE VIEW DR <br />IMPROVEMENTS <br />CIP NO. 3-0-003-09 <br />PROJECTNO. <br />PD-WM-20006-07 <br />5•04.3(16) WeatherLimitations <br />HMA ior wearing course shall not be placed on any traveled way between October 1 of any year <br />and April 1 of the following year without written approval from the Project Engineer. <br />Asphalt for prime coat shall not be applied when the ground temperature is lower than 50°F, <br />without written pertnission of the Engineer. <br />HMA Class D shall not be placed when the air temperature is less than 60°F. <br />HMA shall not be placed on any wet surface, or when the average suriace temperatures are less <br />than those specified in the following table, or when weather condi6ons otherwise prevent the <br />proper handling or finishing of the HMA mixtures: <br />Compacted Thickness <br />(Feet) <br />Less than 0.10 <br />0.10 to 020 <br />0.21 to 0.35 <br />More than 0.35 <br />Surface Temperature Limitations <br />Sub•Surface <br />Surface Course Courses <br />55 F 55 F <br />45 F 35 F <br />35 F 35 F <br />DNA 25 F` <br />'Only on dry subgrade, not frozen and when air temperature is rising. <br />5-04.3(17) Paving Under Tralfic <br />When the roadway being paved is open to traffic, the following requirements shall apply: <br />The Contractor shall keep on-ramps and off•ramps open to traffic at all times except when <br />paving the 2mp or paving across the ramp. During such time, and provided that there has <br />been an advance waming to the public, the ramp may be closed for the minimum time <br />required to piace and compact the HMA. In hot weather, the Project Engineer may require <br />the application of water to the pavement to accelerate the finish rolling of the pavement and <br />to shorten the time required before reopening to lraffic. <br />Before closing a ramp, advance waming signs shall be piaced and signs shall also be <br />placed marking the detour or altemate route. Ramps shall not be closed on consecutive <br />interchanges at the same time. <br />During paving operations, temporary pavement markings shall be maintained throughout <br />the project. Temporary pavement markings shall be installed on the roadway prior to <br />opening to traBic. Temporary pavement markings shall be in accordance with 5ection 8- <br />23. <br />All costs in connection with performing lhe work in acr.ordance with these requirements, <br />except the cost of temporary pavement markings, shall be included in lhe unit contract <br />prices for lhe various bid items involved in the contract. <br />Page 25 of 50 <br />