Laserfiche WebLink
� <br /> ! 1 PROGRESS SCHEDULES <br /> I 2 Description <br /> 3 The Contactor shall submit to the Engineer electronic progress schedules to <br /> 4 demonstrate the Contractor's plan to complete the work in the tim� specified and that <br /> I 5 progress is being made to meet the schedule. <br /> 6 <br /> 7 Submittals <br /> � 8 The following submittals are required. <br /> I 9 <br /> 1 o Submittal Format <br /> � 11 The eiectronic copy shali be submitted on a compact disc and/or as an attachment <br /> � 12 to e-mail per the schedule belew. The electronic copy must be cornpatible Microsoft <br /> 13 Project 2002 in MPP file format. <br /> 14 <br /> � 15 Pre-Award Progress Schedu/e <br /> 16 The Contractor shall submit an electronic copy and one hardcopy of a pre-award <br /> 17 progress schedule (total working de��s) to ihe Engineer before Award of this <br /> I 18 contract. <br /> 1 19 <br /> 20 Preliminary Progress Schedule <br /> � 21 The Contractor shail submit an electrenic copy and one hardcopy of a preliminary <br /> � 22 progress schedule (first 60 working days) to the Engineer no later than five c��lendar <br /> 23 days after lhe date the contract is executed. This preliminary progress schedule <br /> ' 24 shall show work to be performed during the first 60 days of the contract. <br /> � 25 <br /> 26 Progress Schedule <br /> � 27 The Contractor shall submit an electronic copy and one hardcopy of the progress <br /> 28 schedule (total working days) to the Engineer no later than 30 calendar days after <br /> 29 the date the contract is executed. <br /> 30 <br /> I31 Updated Progress Schedu/es <br /> 32 The Contractor shall submit an electronic copy and one hardcopy of the updated <br /> 33 progress schedule (totai working days)to the Engineer by the 5'"day of each month <br /> � 34 throughout the duration of this contract. <br /> � 35 <br /> 36 Contractor's Certifcation <br /> I 37 The Contractor shall submit with each schedule submission, certification that the <br /> 38 progress schedule submission is the actual schedule being utilized for the execution <br /> 39 of the work. <br /> � 40 <br /> � 41 Construction Requirements <br /> 42 The following electronic submittals are required. <br /> 43 <br /> 44 Pre-Award Progress Schedule <br /> 45 Show aciivities including, but not limited to the following: order of and time required <br /> 46 for the various construction phases of work and their major work activities. <br /> 47 <br /> Port of Everett FAWAT•03-039 <br /> ' Satellite RaillBargc Transfnr Facillty Final Port Reviow Drak <br /> Phase 1:Pier Conslruction 21 15 Mareh 2005 <br />