2 Project: Sewer System Replacement"F" Sch C <br /> Change Order No. 1 <br /> Change Order Effective Date: August 14, 2007 <br /> Quantities in these bid items were reduced as part of the agreement for installing <br /> the new concrete pavement, curbs, curb ramps, sidewalks and driveways. <br /> Item #10—Concrete Pavement Patch. <br /> Item #29—Concrete Sidewalk Restoration. <br /> Item #30—Concrete Curb/Curb and Gutter Restoration. <br /> Item #31 —Curb Ramp. <br /> See the attached table outlining estimated net increase costs, and cost savings. <br /> Exhibit C—Additional Contract Time <br /> There will be 12 additional working days added for this change order. <br /> 8 <br /> Page 5 of 5 <br />