Laserfiche WebLink
SCHEDULE B: SMk 'ISLAND LANDFILL 177065B <br />PHASE 2 CLOSURE IMPROVEMENTS <br />3.9 ACCEPTANCE TESTING <br />A. Contractor shall perform in -place density and moisture content tests as <br />specified in Section 02316, Fill and Backf ill, to be observed by the Owner's <br />Representative, on the following minimum schedule: <br />1. Backfill Above Pipe Zone (Non -Waste Trench): One per 500 linear feet <br />per lift. <br />2. Seepage Barrier: One per lift. <br />3.10 MAINTENANCE OF TRENCH BACKFILL <br />A. After each section of trench is backfilled, maintain the surface of the <br />backfilled trench even with the adjacent ground surface until final surface <br />restoration is completed. <br />B. Add excavated material where applicable and keep the surface of the <br />backfilled trench level with the adjacent ground surface. <br />END OF SECTION <br />SEA/177065.A7.19 JULY 16, 2004 <br />02320 5 TRENCH BACKFILL <br />