SECTION 01200 <br />MEASUREMENT AND PAYMENT PROCEDURES <br />c) At the time of submission of the Schedule of ialues, the Contractor shall provide to <br />the Resident Engineer a certification signed by each major subcontractor (those <br />having contract values greater than 5% of the Work). The certification shall state <br />that the Contractor has communicated and coordinated with each major <br />subcontractor in the development of the Schedule of Values, and that the major <br />subcontractors agree to the requirements for timing and duration of activities as <br />stated therein. <br />d) Once the Schedule of Values is approved by Sound Transit, this schedule shall <br />become the official Schedule of Values for progress payment processing. <br />e) The Schedule of Values shall be cost -loaded and, for lump sum bid items, will be <br />the basis for progress payment each month. (For unit price bid items, progress <br />payments will be made according to the Contract Documents.) Cost components <br />shall be assigned to each of the activities identified in Schedule of Values. The <br />sum of the activity cost components shall equal the contract price. The cost of each <br />activity shall be a portion of the lump sum price as it relates to each activity. The <br />cost shall include labor, material, equipment, overhead and fee. Normally, cost for <br />order/delivery activities will not be allowed. The cost of material and equipment <br />shall be associated with the installation of such material and equipment unless <br />otherwise required by the Resident Engineer. The total cost of all activities shall <br />equal the lump sum bid price for the bid item or total contract as applicable. <br />f) On material where the Contractor anticipates requesting payment in advance of <br />installation, it shall be identified as a separate line item in the Schedule of Values. <br />g) The cost -loaded Schedule of Values will be the basis of progress measurement for <br />the contract. The Contractor shall show percent progress/payment due for each <br />activity and the entire contract. As a part of the monthly updating of the CPM <br />Progress Schedule, the Contractor shall generate a Schedule of Values report and <br />a narrative of any changes that have occurred so that the Schedule of Values will <br />truly reflect the status of the Work and the critical path. <br />It) Any changes in the detailed CPM Progress Schedule shall be reflected in the <br />Schedule of Values. <br />3. Applications for Payment: For each application for payment the Contractor shall <br />submit, at a minimum, the following: <br />a) A completed "Application and Certificate for Payment" form shall be submitted to <br />the Resident Engineer each month, and be based on the work completed. <br />b) Contractor's statement regarding payment of prevailing wages. <br />c) Schedule update and supporting narrative, reports, and analysis as required by <br />Section 01323 — Network Analysis Schedules. <br />d) Certification that as -built drawings are current. <br />e) "Affidavit of Amounts Paid to All Businesses'. <br />f) "Monthly EEO/Apprentice Utilization Report". <br />Capital Projects Commuter Rail 01200 - 2 IFB No. RTA/CP 21-06 <br />Everett Station Phase 2 MEASUREMENT AND PAYMENT PROCEDURES <br />