Laserfiche WebLink
SECTION 01330 <br />SUBMITTALS <br />1.08 PROGRESS PAYMENT AND EMPLOYMENT REPORTING <br />A. Make all submittals in accordance with the requirements of the General and Special <br />Prcvisions and these specifications of the Contract. <br />1.09 PROGRESS SCHEDULES <br />A. See Section 01323 Network Analysis Schedules. <br />1.10 PROJECT RECORD DOCUMENTS <br />A. See Section 01729 Project Record Documents. <br />1.11 COORDINATION <br />A. Submit shop and detail drawings in related packages. All equipment or material details that <br />are interdependent or are related in any way must be submitted indicating the complete <br />installation. Submittals shall not be altered once approved for construction. Clearly mark <br />and date revisions. Major revisions must be resubmitted for acceptance. <br />B. Thoroughly review all shop and detail drawings prior to submittal, including all those <br />provided by subcontractors and suppliers at any tier, to assure coordination with other parts <br />of the Work. Submittals shall bear the Contractor's approval stamp and initials of the <br />reviewer. <br />n <br />C. Components or materials which require shop drawings and which arrive at the job site prior <br />to approval of shop drawings shall be rejected and shall be removed by the Contractor from <br />one premises. <br />1.12 UTILITY DEACTIVATION AND REACTIVATION PLANS <br />A. The Contractor shall submit a plan to the Resident Engineer for review. The plan shall <br />outline the proposed procedure to deactivate and reactivate utility services, lines and <br />equipment required to be disrupted, disassembled, cut into, or modified during the course of <br />the Work. <br />Plan Content <br />The plan shall include but not be limited to: <br />1. Shutdown and restart schedules. <br />2. Sequences required to deactivate, depressurize, and reactivate the utility service lines <br />and equipment. <br />3. Detailed description of proof positive verification and/or tests to assure that utility <br />service line and equipment are properly deactivated before proceeding with the work. <br />Capital Projects Commuter Rail 01330 - 3 IFB No. RTA/CP 21-06 <br />Everett Station Phase 2 SUBMITTALS <br />