Laserfiche WebLink
1-08.3(3)B Schedule Contents <br /> All Progress Schedules shall: <br /> 1. Include essential sub-schedules of related activities. <br /> 2. Allow for timely incorporation of any other's work under separate contract with <br /> City. <br /> 3. Allow for timely incorporation of work provided and installed by City. <br /> 4. Include submittals to agencies required for performance of Work with sufficient, <br /> adequate and reasonable time for review,comment and return submittals. <br /> 5. Allow for appropriate durations to complete activities that may be affected by <br /> weather during the time of year the activities are performed. <br /> 6. Identify logical connections, dependency upon preceding or succeeding <br /> activities, restraints or constraints, planned start and completion dates, duration, <br /> actual start and completion dates,and variances. <br /> 7. Activity durations shall not exceed twenty (20) days. The activities shall be <br /> related to early and late start,early and late finish,and Float dates. <br /> Activities listed in the Preliminary Schedule shall be included in all subsequent <br /> schedules. No activity in the Preliminary Schedule shall be deleted without prior written <br /> consent of the Representative and City. <br /> 1111 <br /> Contractor shall notify City's Representative and City in writing and highlight the <br /> addition of all activities to the schedule after the Preliminary Schedule. <br /> The Baseline Schedule shall be part of the Contract. <br /> Each activity shall be identified with a number that incorporates the Specification section <br /> number. <br /> Activities shall be consistent and identified with the Schedule of Values (if applicable)or <br /> unit prices of the bid schedule. All elements and items in the Schedule of Values or unit <br /> prices in the bid schedule shall appear in the Progress Schedules. <br /> Contractor shall provide sub-schedules for each stage/phase of Work as required by City, <br /> City's Representative,or Subcontractor. <br /> Contractor shall provide sub-schedules to define major portions of the entire schedule. <br /> Include long-lead-time items for Equipment and material that requires long fabrication <br /> time. Order these well in advance of required delivery time to sequence with overall <br /> construction schedule. <br /> Each schedule shall show accumulated percentage of completion of each activity, and <br /> total percentage of Work completed, as of the date of payment application. <br /> Contractor shall include in each schedule as activities the submission, review, and <br /> a correction of Submittals, Shop Drawings, Product Data and Samples. The schedule <br /> should show: <br /> 1. The dates for Contractor's Submittals. <br /> 2. A minimum of 14 calendar days duration for City or City's Representative's <br /> review. <br /> 3. Indicate decision data for selection of finishes. <br /> a 4. Show Submittal preparation, submission,review,and breakdown at a minimum. <br /> 5. Show individual parts of major Submittals. <br /> Contractor shall identify any and all Work furnished by City and installed by City on the <br /> construction schedule. <br /> HAYES STREET REGULATOR February, 2017 <br /> AND CSO CONTROLS (SRO1, SRO2,AND SRO3) <br /> a WO No—UP3398-31 SP - 102 <br />