1 <br /> 1-09.9 Payments to Contractors <br /> (******) <br /> 1-09.9(1) Progress Payments <br /> Contractor shall submit progress payment estimate for completed Work and material on hand <br /> based upon acceptable Work performed during the previous month, or since the last partial <br /> payment estimate was submitted. Submit progress payment estimate to City's Representative by <br /> the tenth day of each month, or by schedule mutually agreed upon in writing by the Contractor <br /> and City's Representative at the Pre-Construction Conference. Contractor shall make initial <br /> progress estimate not later than 30 days after the Work begins. Make successive progress <br /> estimates every month thereafter until the Completion Date. <br /> Progress estimates made during progress of the Work are tentative, and made only for the <br /> purpose of determining progress payment. The progress estimates are subject to change at any <br /> time prior to the calculation of the Final Payment. I <br /> The value of the progress estimate will be the sum of the following: <br /> 1. Unit Price Items in the Proposal Form—the approximate quantity of acceptable units <br /> of work completed multiplied by the unit price. <br /> 2. Lump Sum Items in the Proposal Form — the estimated percentage complete <br /> multiplied by the Proposal Forms amount for each Lump Sum Item, or per the <br /> schedule of values for that item. <br /> 3. Materials on Hand— 100 percent of invoiced cost of material delivered to Job site or <br /> other storage area approved by the Engineer. <br /> 4. Change Orders — entitlement for approved extra cost or completed extra work as <br /> determined by the Engineer. <br /> Progress payments will be made in accordance with the progress estimate less: <br /> 1. Retainage in accordance with 1-09.9(6)RETAINAGE, <br /> 2. The amount of Progress Payments previously made,and <br /> 3. Funds withheld by the City for disbursement in accordance with the Contract <br /> Documents. <br /> Progress payments for Work performed shall not be evidence of acceptable performance <br /> or an admission by the City that any Work has been satisfactorily completed. <br /> Payments will be made by warrants, issued by the City's fiscal officer, against the appropriate <br /> fund source for the Project. Payments received on account of Work performed by a <br /> Subcontractor are subject to the provisions of RCW 39.04.250. <br /> Contractor's submission of a progress pay estimate constitutes the Contractor's material <br /> representation that Contractor performed all of the Work described in the progress pay estimate <br /> during the relevant time period in a conformance with these Plans and Specifications and that <br /> the materials or Equipment for which payment is requested reasonably conform to the <br /> Specifications and are either on the job site or have been installed. If requested by the City's <br /> Representative, provide additional data as may be reasonably required to support the payment <br /> estimate. Additional data may include, but not be limited to, satisfactory evidence of payment <br /> for Equipment, materials and labor, including payments to Subcontractors and suppliers. <br /> Certified invoices by the suppliers shall accompany a request for payment for delivered <br /> Equipment and material. Such Equipment and material shall be suitably and safely stored at the <br /> site of the Work. Payment requests shall summarize accepted operating and maintenance <br /> material with request for Equipment payment. <br /> A progress payment is preliminary only. By making a progress payment, the City does not <br /> waive or release its right, nor is it estopped from asserting, that previous progress payments <br /> were not earned or were in error,whether in whole or in part. <br /> I <br /> HAYES STREET REGULATOR February,2017 <br /> AND CSO CONTROLS (SRO1, SRO2,AND SRO3) <br /> WO No–UP3398-31 SP- 119 <br />