I <br /> 7-04.3 Construction Requirements <br /> Add the following: <br /> 7-04.3(1)G Cleaning and Testing <br /> 7-04.3(1)G1 Deflection Test for Thermoplastic Pipe <br /> After trench backfill and compaction are completed, perform deflection testing if <br /> CCTV testing reveals thermoplastic pipe being out of round. <br /> 7-04.3(1)G2 Television Inspection <br /> After trench backfill and compaction are completed the City will use their CCTV <br /> camera to inspect the interior of mains and the interior of existing lines having <br /> Contractor installed new manholes or new side sewers or both. Provide the City with <br /> a three-business-day notice for each CCTV request. Begin final roadway surfacing <br /> AFTER notice from City Inspector of City Sewer Department approval of the CCTV <br /> inspection. <br /> Prior to arranging with City for CCTV inspection, perform the following: <br /> Clean lines and structures of all debris, <br /> Channel manholes inverts, <br /> 3111 Seal pipes entering structures according to these Special Provisions. <br /> Correct deficiencies noted by the City Inspector and the CCTV inspection results to <br /> the satisfaction of the Engineer. <br /> City will bear initial inspection costs. Contractor shall be responsible for re-inspection <br /> costs if CCTV equipment will not pass through the lines or structures on initial <br /> inspection. City will deduct cost for follow-up re-inspection after correction of <br /> deficiencies from Contractor's final payment on a direct cost basis. <br /> 7-04.3(1)H Cleaning and Testing <br /> 7-04.3(1)H1 Final Acceptance <br /> City will require successful completion of the following items prior to issuing final <br /> acceptance, including, but not limited to: <br /> 1. Passing low pressure air testing. <br /> 2. Backfill and compaction in accordance with COE Standard Drawings No. 610, <br /> 611 and 615. <br /> 3. Line and grade to the tolerance of 7-08.3(2)B. <br /> 4. Manhole, inlet,and catch basin to the invert elevation,and cleaned. <br /> 5. Manhole, inlet,and catch basin casting set to final grade. <br /> 6. Manhole, inlet, and catch basin construction in accordance with 7-05.3. <br /> 7. Lines free of debris and obstructions. <br /> 8. Bell and spigot joints properly seated as evidenced by successful completion of <br /> CCTV testing. <br /> 9. Manhole fully channelized. <br /> 7-04.4 Measurement <br /> Delete the first paragraph of 7-04.4 and substitute the following: <br /> Bid items of Work completed pursuant to the Contract Documents will be measured as <br /> described in Division B — Bid Item Descriptions of these Special Provisions and Section 1-09 <br /> I MEASUREMENT AND PAYMENT of the Standard Specifications. <br /> .5 Payment <br /> Delete all paragraphs in 7-04.5 and substitute the following: <br /> I <br /> HAYES STREET REGULATOR February,2017 <br /> AND CSO CONTROLS (SRO1, SRO2,AND SRO3) <br /> WO No—UP3398-31 SP- 162 <br />