I <br /> 1-05.3(2) Requests for Information <br /> (******) <br /> Requests for information or clarification from the Contractor to the City shall be treated as a <br /> Submittal pursuant to 1-05.3(1)SUBMITTALS. <br /> 1-05.4 Conformity With and Deviations From Plans and Stakes <br /> Delete all of 1-05.4 and substitute the following: <br /> The Contractor shall be responsible for setting and maintaining all alignment stakes, slope <br /> stakes, and grades necessary for the construction of the roadbed, surfacing, paving, <br /> channelization, illumination, signing, bridges, and retaining walls, if such construction is <br /> included in this Project. Except for the survey control data to be furnished by the City, <br /> calculations, surveying, and measuring required for setting and maintaining the necessary lines <br /> and grades shall be the Contractor's responsibility. The Contractor shall provide the City with <br /> copies of such calculations and staking data when requested by the Engineer.Copies of the City <br /> 111 <br /> provided survey control data are available for the Bidder's inspection at the office of the Project <br /> Engineer. <br /> Any staking requirements for the Project that do not fit field conditions will be reviewed and if <br /> necessary adjusted by the Engineer. Any necessary revisions to the staking information will be <br /> provided to the Contractor for use in completing the Work. <br /> Stakes, marks, and other reference points, including existing monumentation, set by the City <br /> shall be carefully preserved by the Contractor. The Contractor will be charged for the costs of <br /> replacing stakes, markers and monumentation that were not to be disturbed but were destroyed <br /> or damaged by the Contractor's operations. This charge will be deducted from monies due or to <br /> become due to the Contractor. <br /> To facilitate the establishment of these lines and elevations,the City will provide the Contractor <br /> with the following survey control: <br /> ROADWAY, SURFACING AND PAVING <br /> Establish elevation bench marks and center or base line alignment control points for <br /> the mainline,one time only.Provide right of way stakes where applicable. <br /> Provide rights-of-way, easements or right-of-entry. <br /> Provide the Contractor with technical advice if requested. <br /> Computed grades where needed. <br /> Provide horizontal and vertical curve data. <br /> One copy of transit notes showing reference to horizontal and vertical control points. <br /> OTHER STRUCTURES <br /> Centerline or offset coordinates to centerline of the structure. <br /> A sufficient number of bench marks for levels to enable the Contractor to set grades <br /> at reasonably short distances. <br /> Monuments and control points as shown on the Plans. <br /> The Contractor shall give the City three weeks notification to allow adequate time to <br /> provide the above data. <br /> The Contractor shall ensure a surveying accuracy within the following tolerances: <br /> 1. Slope stakes ±0.1 foot <br /> 2. Subgrade blue tops ±0.01 foot <br /> 3. Stationing ±0.01 foot <br /> 4. Alignment ±0.01 foot <br /> 5. Surfacing red and yellow tops ±0.01 foot <br /> HAYES STREET REGULATOR February,2017 <br /> AND CSO CONTROLS (SRO1, SRO2,AND SRO3) <br /> WO No—UP3398-31 SP - 70 <br />