CITY OF EVERETT SPECIAL PROVISIONS <br /> This Work consists of constructing gravity sanitary or combined sewer mains using <br /> conventional open trench construction methods, as staked, in accordance with the <br /> Plans, these Specifications, and the COE Standard Drawings. <br /> 7-17.2 Materials <br /> Delete list of pipe materials in the first paragraph in 7-17.2 and substitute the following: <br /> Pipes used for sanitary or combined sewers greater than 30-inches in diameter shall be <br /> polypropylene triple wall pipe. Delete the list of material requirements in 7-17.2 and <br /> substitute the following: <br /> Provide materials meeting the following requirements. I <br /> Polypropylene Triple Wall 9-05.24 Special Provisions <br /> Sanitary Sewer Pipe <br /> 7-17.3 Construction Requirements <br /> 7-17.3(2) Cleaning and Testing <br /> 7-17.3(2)G Deflection Test for Thermoplastic Pipe <br /> Revise the first sentence of 7-17.3(2)G to read as follows: <br /> After trench backfill and compaction are completed, perform deflection testing <br /> if CCTV testing reveals thermoplastic pipe being out of round. 1 <br /> 7-17.3(2)H Television Inspection <br /> Delete all three paragraphs of 7-17.3(2)H and substitute the following: <br /> After trench backfill and compaction are completed the City will use their <br /> CCTV camera to inspect the interior of mains and the interior of existing lines <br /> having Contractor installed new manholes or new side sewers or both. <br /> Provide the City with three business days notice for each CCTV request. <br /> Begin final roadway surfacing AFTER notice from City Inspector of City Sewer <br /> Department approval of the CCTV inspection. <br /> Prior to arranging with City for CCTV inspection, perform the following: <br /> Clean lines and structures of all debris, <br /> Channel manholes inverts. <br /> Seal pipes entering structures according to these Special Provisions. <br /> Correct deficiencies noted by the City Inspector and the CCTV inspection <br /> results to the satisfaction of the Engineer. <br /> City will bear initial inspection costs. Contractor shall be responsible for re- <br /> inspection costs if CCTV equipment will not pass through the lines or <br /> structures on initial inspection. City will deduct cost for follow-up re-inspection <br /> after correction of deficiencies from Contractor's final payment on a direct <br /> cost basis. <br /> 7-17.3(2) Cleaning and Testing <br /> Supplement 7-17.3(2) by adding the following: <br /> 7-17.3(2)1 Final Acceptance <br /> (******) 1 <br /> City will require successful completion of the following items prior to issuing final <br /> acceptance, including, but not limited to: <br /> 1. Passing low pressure air testing. <br /> 2. Backfill and compaction in accordance with COE Standard Drawings No. <br /> 614, 615 and 620. <br /> 3. Line and grade to the tolerance of 7-08.2(2)B. I <br /> Sewer Regulators R4 and Division 7—STORM,SEWER,WATER May 2017 <br /> R39 Modifications <br /> WO No.—UP3633 SP-178 <br />