CITY OF EVERETT SPECIAL PROVISIONS
<br /> Items not included in this item include, but are not limited to:
<br /> (a) Work covered by a specific bid item or Work that is to be included in a bid item
<br /> or items.
<br /> (b) Profit, interest on borrowed money, overhead or management costs.
<br /> Partial payments will be made for the lump sum contract price for "Mobilization and
<br /> Demobilization R39 Site" as follows:
<br /> 111
<br /> (a) When 5% of the total original contract amount is earned from other bid items,
<br /> 50% of the amount bid for mobilization and demobilization, or 5% of the total
<br /> original contract amount, whichever is the least, will be paid.
<br /> (b) When 10% of the total original contract amount is earned from other bid items,
<br /> 50% of the amount bid for mobilization and demobilization, or 5% of the total
<br /> contract amount, whichever is the least, will be paid.
<br /> Upon completion of all work on the project, payment of any amount bid for mobilization and
<br /> demobilization in excess of 10% of the total original contract amount will be paid.
<br /> Bid Item 3 - Temporary Erosion and Sediment Control I
<br /> Measurement and Payment: Lump Sum
<br /> Measurement for Temporary Erosion and Sediment Control shall be the ratio of the number
<br /> of working days completed to the total number of working days authorized in the Contract.
<br /> Temporary Erosion and Sediment Control shall constitute full compensation for all labor,
<br /> materials, tools and equipment necessary and incidental for the installation, maintenance
<br /> and removal of the temporary erosion and sedimentation control (TESC) facilities to
<br /> prevent pollution, erosion, siltation, and damage to any wetland, stream, other watercourse,
<br /> or surrounding property throughout the life of the Contract. TESC facilities shall include,
<br /> but not be limited to, any cover measures, runoff control measures, soil and site
<br /> stabilization measures, filter fabric fencing as shown on the Plans, and inlet protection
<br /> measures for the work area and downstream areas.
<br /> The TESC measures shall limit the erosion possibility by covering disturbed soils,
<br /> preventing sloughing or raveling of cut and natural slopes, and controlling surface runoff
<br /> from flowing into excavations using measures such as curbs, berms, dikes, rock-lined
<br /> ditches, and other approved measures. Filter fabric fence shall be used to treat small
<br /> areas of non-concentrated runoff prior to discharge from the site.
<br /> Bid Item 4 - Surveying
<br /> Measurement and Payment: Lump Sum
<br /> Measurement for surveying will be the ratio of actual pipe installed and backfilled to the
<br /> total quantity of pipe listed in the Proposal.
<br /> The lump sum bid for surveying includes, but is not limited to, all costs associated with
<br /> furnishing all labor, tools, survey instruments materials, and other equipment necessary for
<br /> the setting and monitoring the location, elevation, alignment and grade of the Work as
<br /> specified in 1-05.4 CONFORMITY WITH AND DEVIATIONS FROM PLANS AND STAKES
<br /> and the Plans.
<br /> The lump sum bid item also includes, but is not limited to, all costs associated with I
<br /> furnishing all labor, tools, survey instruments, materials and other equipment necessary for
<br /> verifying the rim and invert elevations, prior to construction, of all existing manholes and
<br /> pipes where connections are to be made.
<br /> The lump sum also includes, but is not limited to, all costs associated with furnishing all
<br /> labor, tools, survey instruments, materials and other equipment necessary for obtaining the
<br /> "as constructed" location and elevations of the Work, in particular, sewer pipe invert I
<br /> Sewer Regulators R4 and Division B—BID ITEM DESCRIPTIONS May 2017
<br /> R39 Modifications
<br /> WO No—UP3633 SP-4
<br />
|