Laserfiche WebLink
t <br /> 4 <br /> ■ RFIs—as of August 1st there are 38 RFIs and BHC and the subconsultant team are projected to address 40 <br /> additional RFIs for the remainder of the project for a total of 78 RFIs. The Task Order 13 budget for BHC's <br /> effort was developed for 20 RFIs. <br /> ■ Meetings-Meetings through August occurred weekly instead of biweekly as budgeted. <br /> ■ Contractor guidance and claim response-several issues have required extensive contractor guidance and <br /> some have included drawing revisions,or contract change initiatives including the following: <br /> o Held special shoring/dewatering meeting on June 16,2015. <br /> o Provided a large number of submittal reviews for the shoring and dewatering systems proposed at <br /> LS33 including Submittals 8,8A,8B,4,4A,4B and 4C. Submittals are budgeted for two reviews,one <br /> initial and one resubmittal. The proposed shoring and dewatering systems required a greater number <br /> of reviews due to site challenges and quality of the submittals. <br /> o Relocated LS33 influent pipe—at the contractors request BHC revised the influent pipe alignment, <br /> changed pipe material to accommodate dewatering challenges and modified peat excavationlremoval <br /> requirements to accommodate pipe type. <br /> o Relocated LS43 at MSI's request to provide additional protection of nearby retaining wall and to <br /> accommodate contractors oversized shoring. <br /> o Addressed MSI's settlement question for pipes located in 36th street. <br /> o Addressed MSI/Axis's claim for additional compensation at LS33. <br /> • Geotechnical Support-Geotechnical issues at this challenging site have resulted in additional effort, <br /> including: <br /> o Increased submittal response effort: Based on the quality of McClure and Sons various geotechnical <br /> related submittals,BHC and HWA have had to spend considerably more time responding to submittals <br /> and contractor plans than anticipated. <br /> o Provided new earth pressure diagram for LS43 retaining wall. <br /> o Increased duration of sheet pile installation-HWA has had to spend more time dealing with temporary <br /> shoring issues that have come up due to MSI not following recommendations at LS43. In development <br /> of the scope and budget,HWA assumed the contractor would require approximately 5 full days to install <br /> the sheets for each lift station temporary shoring system. MSI and Axis Crane took longer than the <br /> anticipated duration to install the sheets. This hs required HWA to have their inspector on site for a <br /> greater amount of time than ant!cip..ated. For LS33,the increased time was largely due to encountering <br /> obstructions. The rate of production for LS43 was even worse than LS33 due to refuse and also due to <br /> MSI's use of sheet piles that went against HWA's recommendations for this location. <br /> o Completed additional resident engineer inspection-The City asked HWA to provide these services <br /> while Don Snyder was on vacation and when the contractor encountered more problems with the <br /> shoring installation at LS43. <br /> o Monitored deep dewatering well installation—The City asked HWA to monitor the installation of the <br /> contractor proposed dewatering wells at LS43 that extend down into the confined aquifer below. The <br /> purpose of HWA's monitoring was to confirm proper well installation and seal placement for the deep <br /> • <br /> • wells. If the wells are not installed properly,contamination at this location is possible because leachate <br /> from the landfill is perched above a relatively clean confined aquifer. Deep wells and other conduits <br /> that pass through the aquitard(hydraulic barrier above the confined aquifer)present a possible route for <br /> leachate to pass to the confined aquifer below. Shallow wells that do not reach the aquifer below do <br /> not pose this same contamination risk. HWA's efforts to observe the deep well installation were not <br /> part of the original Construction Services Scope,because only shallow wells were anticipated for <br /> contractors dewatering system. The deep wells were later proposed by the contractor during <br /> construction after the scope of work had been established. <br /> 21.E r7 <br /> 20 October 2 P 2g. of S <br /> ciDrtcuL P,14f:_ <br />