The test plan shall be reviewed and approved by the Owner's Representative prior to conducting the <br /> test. <br /> 8.1.2 Conduct of Tests <br /> Design-Builder shall not initiate tests until clearwell interiors are dry.Testing shall be satisfactorily <br /> completed,as agreed to by Owner's Representative, prior to initiating East Clearwell water-tightness <br /> testing. <br /> Design-Builder shall notify Owner's Representative of each test, and shall allow Owner's <br /> Representative access to the clearwell interior during testing. Design-Builder shall video document <br /> the results of the tests. <br /> If testing results in visible leaks through the roof, including access hatches and connection points, <br /> Design-Builder shall investigate and repair the source of the leaks and re-test until satisfactory. <br /> results are obtained. A visible leak is defined as an observed stream or ongoing drip of water into the <br /> interior of the clearwell. <br /> Nothing in this Article shall waive Design-Builder's warranty obligations under the Contract <br /> Documents. <br /> 8.2 Clearwell Leakage <br /> 8.2.2 Test Plan <br /> After construction is complete and prior to disinfection, Design Builder shall conduct leakage testing <br /> consistent with the methods used by the City, described in Article 4, Section 4.6.4. <br /> If testing results reveal leakage greater than 31,000 gpd, Design-Builder shall investigate and repair <br /> the source of the leaks and re-test until satisfactory. <br /> Testing shall be satisfactorily completed, as agreed to by Owner's Representative, prior to initiating <br /> East Clearwell disinfection. <br /> ARTICLE 9. SUBMITTALS AND MEETINGS <br /> 9.1 Interim Design Submissions <br /> At a minimum,the Design-Builder shall submit the following items as part of interim design <br /> submissions as described in Article 2.4 of the General Conditions of the Contract. <br /> 1. 50%, 90%, and final Construction Documents including design criteria, drawings, and <br /> specifications <br /> 2. Structural Engineer's Report as required under Article 4, Section 4.4 (with 50%design) <br /> 3. Demolition Plans for the East Clearwell roof system and Screen House Bridge <br /> 4. Schedule for fabrication and notice to allow Owner's Representative to inspect the fabrication <br /> 9.2 Construction Submissions <br /> Design-Builder shall provide the following construction submittals at a minimum: <br /> City of Everett September 13,2017 <br /> Water Filtration Plant Clearwell Roof Replacement DB Project Supplementary Conditions Page 24 <br />