I <br /> If the Contractor requests that more than one (1) copy of the reviewed submittal be returned, 111 <br /> then the Contractor shall submit the appropriate quantity of submittals. <br /> I. For each submittal for review, allow not less than 14 working days for Engineer review, <br /> excluding delivery time to and from Contractor. <br /> J. Identify variations in Contract Documents and product or system limitations that may be <br /> detrimental to successful performance of completed Work. <br /> K. Allow space on submittals for Contractor and Engineer review stamps or comments. ! <br /> L. When revised for resubmission, the Contractor shall identify changes made since previous <br /> submission. A narrative of changes shall be provided,and shop drawings or calculations shall 1 <br /> indicate that a revision was made. <br /> M. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report <br /> inability to comply with requirements. <br /> N. Submittals not requested will not be recognized nor processed. <br /> O. Incomplete Submittals: Engineer will not review. Complete submittals for each item are <br /> required. Delays resulting from incomplete submittals are not the responsibility of Engineer. <br /> 1.6 PRODUCT DATA <br /> A. Product Data:Action Submittal: Submit to Engineer for review for assessing conformance with <br /> information given and design concept expressed in Contract Documents. Submitted data shall <br /> be sufficient in detail for determination of compliance with the Contract Documents. <br /> B. Mark each copy to identify applicable products, models, options, and other data. Supplement I' <br /> manufacturers'standard data to provide information specific to this Project. <br /> 1. Note submittal will be returned to Contractor without review of submittal if products, I <br /> models,options and other data are not clearly marked or identified. <br /> • <br /> C. Indicate product utility and electrical characteristics, utility connection requirements, and <br /> location of utility outlets for service for functional equipment and appliances. <br /> D. After review, produce copies and distribute according to "Submittal Procedures" Article and <br /> for record documents. <br /> 1.7 SHOP DRAWINGS <br /> A. Shop Drawings: Action Submittal: Submit to Engineer for assessing conformance with <br /> information given and design concept expressed in Contract Documents. <br /> B. Indicate special utility and electrical characteristics, utility connection requirements, and <br /> location of utility outlets for service for functional equipment and appliances. <br /> C. When required by individual Specification Sections,provide Shop Drawings signed and sealed <br /> by a professional Engineer licensed in the state of Project responsible for designing <br /> components shown on Shop Drawings. I <br /> Legion Golf Course Stormwater Detention Project Submittal Procedures <br /> WO#UP3620 01 33 00 -4 <br />