My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Rodarte Construction Inc 2/14/2018
>
Contracts
>
Capital Contract
>
Rodarte Construction Inc 2/14/2018
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
11/20/2019 9:56:41 AM
Creation date
2/20/2018 9:52:10 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
Rodarte Construction Inc
Approval Date
2/14/2018
Council Approval Date
1/24/2018
Department
Public Works
Department Project Manager
Nasr Souheil
Subject / Project Title
Legion Golf Course Stormwater Detention
Public Works WO Number
UP3620
Tracking Number
0001067
Total Compensation
$3,760,658.25
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
Document Relationships
Rodarte Construction Inc 10/30/2019 Change Order 3
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
RODARTE CONSTRUCTION INC 12/18/2018 Change Order 1
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
RODARTE CONSTRUCTION INC. 6/12/2019 Change Order 2
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
398
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
I <br /> PART 2 PRODUCTS <br /> 2.1 CONSTRUCTION PROGRESS SCHEDULES <br /> A. Within fourteen(14) days after date of Notice to Proceed, prepare and submit to the Engineer <br /> a practicable schedule showing the order in which the Contractor proposes to carry out the <br /> Work, the dates on which the important features of the work will start, and the contemplated <br /> dates for completing same. In addition to a time-scaled bar chart schedule depicting the project <br /> critical path,the Contractor shall submit a detailed CPM logic diagram.The CPM diagram and <br /> time-scaled bar chart shall include the following: <br /> • Construction activities <br /> • Submittal and approval of material samples and shop drawings <br /> • Procurement of critical materials <br /> • Fabrication,installation, and testing of special material and equipment <br /> • Duration of work, including completion times of all stages and their sub-phases <br /> The activities shall be separately identifiable by coding or use of sub-networks or both. The <br /> duration of each activity shall be verifiable by manpower and equipment allocation,in common <br /> units of measure,or by delivery dates and shall be justifiable by the Contractor upon the request <br /> of the Engineer. <br /> �1 Detailed subnetworks will include all necessary activities and logic connectors to describe the <br /> work and all restrictions to it.In the restraints,include those activities from the project schedule <br /> which initiated the subnetwork as well as those restrained by it. <br /> Include a tabulation of each activity in the computer mathematical analysis of the network <br /> diagram. Furnish the following information as a minimum for each activity: <br /> • Event(node)number(s) for each activity <br /> • Activity description <br /> • Original duration of activities (in normal workdays) <br /> • Estimated remaining duration of activities(in normal workdays) <br /> • Earliest start date or actual start date(by calendar date) <br /> • Earliest finish date or actual finish date(by calendar date) <br /> • Latest start date (by calendar date) <br /> • Latest finish date(by calendar date) <br /> • Slack or float time(in workdays) <br /> Computer printouts shall consist of at least a node sort and an"early start/total-float" sort. <br /> B. Attention is drawn to typical local climatic weather patterns and Work shall be coordinated <br /> accordingly. <br /> C. Complete project schedule shall be revised and resubmitted to the Engineer at a minimum <br /> occurrence of every four(4)weeks for review. <br /> D. Three Week Lookahead Schedules: Provide each week at the weekly construction meeting. <br /> The previous week's completed work shall be shown on the schedule for a total of 4 weeks <br /> shown. <br /> Legion Golf Course Stormwater Detention Project Submittal Procedures <br /> WO#UP3620 01 33 00-7 <br />
The URL can be used to link to this page
Your browser does not support the video tag.