I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> that it may not rely upon receiving the City's response to a Submittal in less than 14 <br /> calendar days, unless the City explicitly changes this section by a signed Change <br /> Order. <br /> 1-05.3(2) Requests for Information <br /> (******) <br /> Requests for information or clarification from the Contractor to the City shall be treated <br /> as a Submittal pursuant to 1-05.3(1) SUBMITTALS. <br /> 1-05A Conformity With and Deviations From Plans and Stakes I <br /> Delete all of 1-05.4 and substitute the following: <br /> The Contractor shall be responsible for setting and maintaining all alignment stakes, <br /> slope stakes, and grades necessary for the construction of the roadbed, surfacing, <br /> paving, channelization, illumination, signing, bridges, and retaining walls, if such <br /> construction is included in this Project. Except for the survey control data to be <br /> furnished by the City, calculations, surveying, and measuring required for setting and <br /> maintaining the necessary lines and grades shall be the Contractor's responsibility. <br /> The Contractor shall provide the City with copies of such calculations and staking data <br /> when requested by the Engineer. Copies of the City provided survey control data are <br /> available for the Bidder's inspection at the office of the Project Engineer. 111 <br /> Any staking requirements for the Project that do not fit field conditions will be reviewed <br /> and if necessary adjusted by the Engineer. Any necessary revisions to the staking <br /> information will be provided to the Contractor for use in completing the Work. <br /> Stakes, marks, and other reference points, including existing monumentation, set by <br /> the City shall be carefully preserved by the Contractor. The Contractor will be charged <br /> for the costs of replacing stakes, markers and monumentation that were not to be <br /> disturbed but were destroyed or damaged by the Contractor's operations. This charge <br /> will be deducted from monies due or to become due to the Contractor. <br /> To facilitate the establishment of these lines and elevations, the City will provide the <br /> Contractor with the following survey control: <br /> ROADWAY, SURFACING AND PAVING <br /> Establish elevation bench marks and center or base line alignment control <br /> points for the mainline, one time only. Provide right of way stakes where <br /> applicable. <br /> Provide rights-of-way, easements or right-of-entry. I <br /> Provide the Contractor with technical advice if requested. <br /> Computed grades where needed. <br /> Provide horizontal and vertical curve data. <br /> One copy of transit notes showing reference to horizontal and vertical control <br /> points. <br /> OTHER STRUCTURES <br /> Centerline or offset coordinates to centerline of the structure. <br /> A sufficient number of bench marks for levels to enable the Contractor to set <br /> grades at reasonably short distances. <br /> Monuments and control points as shown on the Plans. <br /> The Contractor shall give the City three weeks notification to allow adequate <br /> time to provide the above data. <br /> The Contractor shall ensure a surveying accuracy within the following tolerances: <br /> Water Main Replacement"S" Division 1 —GENERAL REQUIREMENTS January 29, 2018 <br /> WO No—UP3664 SP—60 <br /> I <br />