Laserfiche WebLink
The project schedule includes time for project review by the City after each design milestone. WRK will <br /> issue review packages after the Technical Summary Memorandum,the 75%Construction Documents set <br /> and 100%Construction Documents/Bid/Permit Set. <br /> SERVICE CENTER PROJECT SCHEDULE <br /> Project Milestone Date <br /> Anticipated Notice to Proceed &Project Kick-off Meeting December 3,2018 <br /> Building walk through December 4,2018 <br /> Submit Technical Summary Memo to City December 17, 2018 <br /> Meeting with City-Review strengthening options and select best January 22,2019 <br /> value concepts to achieve target building rating <br /> Submit Schematic Design Documents to City February 28, 2019 <br /> Meeting with City-Review SD documents and finalize March 14,2019 <br /> strengthening measures <br /> Submit 75%Construction Documents to City April 30, 2019 <br /> Meeting with City to review 75%CD's May 7,2019 <br /> Submit 100%Construction Documents/Bid Set/Permit Set to City June 24, 2019 <br /> • <br /> Page 7 of 7 <br />