Laserfiche WebLink
City of Everett 00 7200 - 34 ' <br /> Evergreen Branch Library Expansion 2017-008 <br /> 9.5. ADJUSTMENT OF CONTRACT SUM <br /> 9.5.1 Calculation <br /> Except as otherwise expressly provided in these General Conditions,any and all adjustments of Contract <br /> Sum shall be determined as follows: <br /> 1. If the parties are able to agree, the price will be determined by using: ' <br /> a. Unit prices,if the Work items are defined by unit prices; and <br /> b. Other prices agreed upon by the Contractor and Owner for Work not defined by unit prices. <br /> 2. If the parties cannot agree,the Owner's Representative will determine the price pursuant to the <br /> following order: <br /> a. Unit prices,if the Work items are defined by unit prices; and ' <br /> b. Other means to establish the reasonable cost of the Work if it is not defined by unit prices, <br /> including,but not limited to,Force Account as described in 9.6.FORCE ACCOUNT,the <br /> Schedule of Values,or estimating manuals. ' <br /> 9.5.2 . Limitations <br /> The following limitations shall apply in determining the amount of an adjustment: <br /> 1. : Except as otherwise expressly provided,Contractor will only be paid for costs it clearly and <br /> convincingly proves it actually and directly incurred,and shall not include consequential or indirect <br /> damages not otherwise expressly permitted by the Contract Documents. Costs and damages for <br /> which Owner shall not be liable under any circumstances include,but are not limited to: (a) <br /> borrowing or interest costs,charges,or expenses of Contractor;(b)alleged lost profit or Overhead <br /> on any other project;and(c)Contractor's failure or inability to obtain other work. <br /> 2. No Contract Claim for adjustment of Contract Sum or additional compensation for extra,affected, <br /> impacted or inefficient Work will be allowed where the Contractor does not keep and maintain <br /> contemporaneous,complete and accurate time records for labor and equipment and <br /> contemporaneous,complete and accurate records for materials and where such records do not <br /> contemporaneously segregate and allocate by time, location and work the time and costs for each <br /> item or element of such work Contractor's failure to keep and maintain such records constitutes a <br /> waiver of any Contract Claim or request by the Contractor for adjustment of Contract Sum for such <br /> costs or event. <br /> 3. To the extent the Contractor is entitled to an adjustment of Contract Sum due to any Delay or <br /> extension of Contract Time,Contractor shall be compensated as provided in 12.4 REMEDIES. <br /> Such compensation shall be full,adequate and complete compensation for all direct,indirect, <br /> cumulative,inefficiency,impact and ripple costs causing, arising out of,or relating to such delays <br /> or extension. , <br /> 4. Contractor and Owner agree that compensation to the Contractor for a Contract Claim shall not <br /> exceed the Contractor's costs based upon Force Account as described in 9.6.FORCE ACCOUNT. <br /> Contractor waives,releases,and agrees not to submit any request for adjustment of Contract Sum or <br /> Contract Claim based upon a"total cost"or"modified total cost"calculation,in whole or in part, <br /> but instead agrees that any and all requests for compensation shall be based upon accurate,complete <br /> and contemporaneous cost records that segregate and allocate costs(a)between base Contract Work <br /> and the work for which additional compensation is sought and(b)between each item of work for <br /> which additional compensation is sought. Claims for inefficiency shall only be based and <br /> calculated by a comparison of productivity of similar Work performed in an unaffected or least <br /> affected area of the Project. <br /> 5. No claim for consequential damages of any kind will be allowed. <br /> 1 <br /> 00 7200 - 34 GENERAL CONDITIONS <br />