Laserfiche WebLink
Project-Water Main Replacement Q Evergreen Way Rebid <br /> Change Order No. 001 <br /> Change Order Effective Date: March 1, 2019 <br /> Added Bid Items <br /> New Item 101 —Full Lane Pavement Grind. Add new item# 101 entitled, "Full Lane Pavement <br /> Grind" at the agreed to lump sum price of$26,740.00, resulting in a$26,740.00 increase to the <br /> Contract price. <br /> New Item 102—Adjust Valve Boxes. Add new item 102 entitled"Adjust Valve Boxes", to increase <br /> contract value at agreed unit price of$1,230.00 per EA,by adding 20 EA, resulting in a$24,600.00 <br /> increase to the contract. <br /> New Item 103 Adjust Catch Basins. Add new item 103 entitled"Adjust Catch Basins",to increase <br /> contract value at agreed unit price of$1,695.00 per EA,by adding 5 EA,resulting in a$8,475.00 <br /> increase to the contract. <br /> Washington State Sales Tax <br /> An increase to the contract in the amount of$16,105.32 is included for the estimated sales tax <br /> payment. <br /> JUSTIFICATION <br /> Bid Items; 4 Traffic Control Labor, 14 Gravel Borrow,27 Water Service Line 1", 33 Permanent <br /> HMA Patch and 38 Vehicle Detection Loops-These items over-ran the estimated plan quantity <br /> which requires addition funding. <br /> Bid Items; 13 Foundation Material, 32 Cement Concrete Base and, and 38 Permanent Pavement <br /> Markings—There was no work associated with these items therefore the quantity is being reduced to <br /> zero. <br /> New Items; 101 Full Lane Pavement Grinding, 102 Adjust Valve Boxes and 103 Adjust Catch <br /> Basins. These are added as compensation for expanding pavement restoration from trench patch width <br /> to full lane width. <br /> Washington State Sales Tax <br /> All changed work represented in subject to WAC 458-20-170 which requires the contractor to collect <br /> sales tax. <br /> Contract Duration—There are no changes in the contract duration due to these changes <br /> Page 4 of 5 <br />